The installation of low-voltage switchgear requires following certain steps:


Determine installation location: The installation location of the low-voltage switchgear should be determined based on the design drawings and confirmed.


Assembly: Assemble each part according to the instructions and plan, including installing unit modules, crossbeams, bases, end plates, etc., and inspect them after assembly.


Connecting cables: According to the wiring diagram, connect the low-voltage switchgear to the corresponding cables, paying attention to the correct insertion of the wiring terminals.


Grounding: Ensure good grounding between the low-voltage switchgear and equipment, and conduct grounding tests if necessary to ensure correct connection.


Debugging: After installation, debugging should be carried out to check whether various functions and performance indicators are normal, and calibration and adjustment should be carried out if necessary.


Implement protective measures: Necessary protective measures should be implemented according to the installation environment and relevant regulations, such as lightning protection, water seepage protection, etc.


Finally, conduct a comprehensive testing and inspection of the low-voltage switchgear to ensure its normal operation and achieve the expected functions, effects, and safety requirements.